AIA A201, A401 and A701 basics for the Florida Business & Finance exam
Three AIA contract documents are on DBPR's Business & Finance reference list. Questions on bids, contracts, payments and disputes often come back to them. Below is a summary in our own words with section numbers. Always read the documents themselves.
| Document | Edition | What it is |
|---|---|---|
| A201 | 2017 | General Conditions of the Contract for Construction: the rules between owner and contractor, with the architect's role |
| A401 | 2017 | Standard Form of Agreement Between Contractor and Subcontractor |
| A701 | 2018 | Instructions to Bidders: how bids are prepared, submitted, changed and secured |
A201–2017: numbers worth tabbing
| Section | Topic | Key point |
|---|---|---|
| 2.5 | Owner's right to carry out the Work | If the contractor doesn't start correcting a default within a ten-day period after the owner's notice, the owner may correct it. |
| 7.2.1 | Change Orders | Written, prepared by the architect, and signed by the owner, contractor and architect. |
| 9.3.1 | Applications for Payment | Submitted to the architect at least ten days before each progress payment date. |
| 9.7 | Failure of payment | If the architect doesn't certify within seven days, or the owner doesn't pay within seven days of the due date, the contractor may stop work after seven more days' notice. |
| 9.8.1 | Substantial Completion | The Work is complete enough that the owner can occupy or use it for its intended purpose. |
| 12.2.2.1 | Correction period | One year after Substantial Completion. |
| 14.1.1 | Termination by the contractor | Possible if the Work is stopped for 30 consecutive days, through no fault of the contractor, for the listed reasons. |
| 15.1.2 | Time limit on claims | Not more than 10 years after Substantial Completion. |
| 15.1.3.1 | Notice of claims | Within 21 days after the event, or after the claimant first recognizes the condition, whichever is later. |
| 15.3.1 | Mediation | Mediation is a condition precedent to binding dispute resolution, with stated exceptions. |
Studying for the Business & Finance exam? The full course has 300 original practice questions, each pointing to the reference to check, plus a 120-question timed exam, in English and Spanish. $49 one time (Black Friday price, reg. $79, ends Dec 1), 14-day money-back guarantee.
See the full courseA401–2017: the subcontract
- Flow-down (Article 2): the subcontractor takes on toward the contractor the obligations the contractor has toward the owner and architect, to the extent the prime contract applies to the subcontractor's work.
- Directions (3.3.2): the contractor doesn't give orders directly to the subcontractor's employees, sub-subcontractors or suppliers unless they're the subcontractor's authorized representatives.
- Suspension (7.3.1): the contractor may suspend the subcontract work in writing without cause, and the subcontractor gets an equitable adjustment of time and price.
- Progress payments (11.1.3): the contractor pays the subcontractor no later than seven working days after receiving payment from the owner.
- Retainage (11.1.8): the parties fill in the retainage percentage or amount.
A701–2018: bidding
- Bid security (4.2.1–4.2.3): if a bidder refuses to enter into the contract or furnish required bonds, the bid security is forfeited to the owner as liquidated damages, not as a penalty. A bid bond is written on AIA A310 unless the bidding documents say otherwise.
- Changing or withdrawing a bid (4.4.1–4.4.2): allowed by notice before the time set for receiving bids. Withdrawn bids may be resubmitted before that time.
- Clerical errors (4.4.3): after bids are received, a bidder who finds a clerical error notifies the architect within two days, or within the period set by local law.
- Bonds (7.2.2): performance and payment bonds are written on AIA A312 unless otherwise provided.
Where to buy: the reference list points to the American Institute of Architects and the Florida Association of the AIA. Read the tabbing rules before you tab them.
Sources: DBPR Business & Finance Reference List, 2026 · AIA Contract Documents (A201–2017, A401–2017, A701–2018 text). Checked November 2026. Always confirm the current documents before you buy books or book your exam.
Frequently asked questions
Which AIA documents are on the Florida Business & Finance exam?
DBPR's 2026 and 2027 reference lists include AIA A201 (2017), A401 (2017) and A701 (2018).
Under A201-2017, how long does a party have to start a claim?
Section 15.1.3.1 says claims must be initiated within 21 days after the event giving rise to the claim, or within 21 days after the claimant first recognizes the condition, whichever is later.
What is the A201-2017 correction period?
Generally one year after the date of Substantial Completion, under Section 12.2.2.1.
When must a contractor pay a subcontractor under A401-2017?
Section 11.1.3 says no later than seven working days after the contractor receives payment from the owner.
Practice with the full course
300 original practice questions with every answer pointed to the reference to check, a full 120-question timed exam with unlimited retakes, and a complete Spanish version. $49 one time (Black Friday price, reg. $79, ends Dec 1), no subscription, 14-day no-questions refund.
Get full access: $4914-day money-back guarantee · Terms
Take the free 10-question quiz first